Smart Turnkey Solution For Building Complex In San Antonio, Tx

THE PROPOSAL

After a technical assessment, ONPEAK Energy proposed that OPT San Antonio replace four air-cooled chillers with new efficient ones and upgrade their building management system.

In addition to these upgrades, OnPeak proposed the following:

– New pumps and valves
– New hot gas bypass
– A voltage protection system
– A ground fault protection

 

THE SOLUTION

ONPEAK installed 4 Daikin Scroll Air Cooled Chillers, equipped with BacNet cards that enabled them to communicate with the new Building Management System (BMS).

A new BMS system was custom designed and installed for the property. Complete with a web-based graphics platform, this new system allowed Accesso to have remote control of all 8 chillers and all 8 AHU. In addition, new sensors with an access control system were provided for the BMS.

Previous
Next

THE OUTCOME

ONPEAK successfully created a customized turnkey solution that resulted in no negative cash flow. This allowed the customer to achieve project completion without impacting their budget. The project has an IRR of 28% with an NPV close to $400k.

The newly installed air cooled chillers, which include a five-year part and labor warranty, assure building’s tenants experience comfort.

Key results of this project include:

– Savings of $100,000 every year in maintenance and power
– Remote control of mechanical equipment
– $8,000 rebate from the utility company
– A reduction of 751,860 kWh each year
– Reduction in greenhouse emissions (CO2) of 586 tons/year

 

Industry

60 months

Technology

High Efficiency Smart HVAC Systems Cooling towers

Expected
Savings

$100,000 /year

Annual KWH
Reduction

751,860

CO2
Reduction

1,172,151 lbs/year

Location

San Antonio, TX